The company has numerous project references. The total installed capacity of these projects is over 1,000 MW, their total value is in excess of 2 billion EUR. In the years since the company's establishment, we have successfully completed or are still involved in over 200 projects. The projects that HSE Invest has been participating in include hydroelectric plants with capacities ranging from 0.2 to 185 MW with spillway structures up to a discharge of 4000 m3/s, and thermal power plants up to 600 MW capacity.

Construction of Borovlje SHPP
Client SEL d.o.o.
Realization year 2015-2020
Construction of Borovlje SHPP
HSE Invest prepared the complete design documentation - design for obtaining a building permit (PGD), detailed design (PZI), as-build design (PID) and the operation and maintenance instructions (NOV) - for the powerhouse with all the auxiliary equipment (electrical, mechanical, hydro mechanical) and all of the exterior arrangements, and obtained the building permit.

Borovlje SHPP is a small hydroelectric power plant located on the left bank of the Javornik dam on the Sava River, with a vertical Kaplan type turbine with installed capacity of 394 kW at installed discharge of 8 m3/s.  The operating licence for the plant was obtained on 10.11.2020. The building permit was obtained on 28.2.2018.

 
Back to list
© Copyright HSE Invest 2016. All rights reserved.  
Graphic and technical implementation BuyITC d.o.o.